Construction Update
Construction crews have made substantial progress on the streetscape project. Village Manager, Bryan White says that crews will concentrate on the west side of Main Street before moving on to the east side. White noted that areas north of the current construction, including the southeast corner of Main and High Street, still need completion. The New York State Department of Transportation set an October 1 deadline to finish bridge work.
Crews will continue to remove, prepare, and install curbing on the west side of Main Street between the lift bridge and Church Street. From the lift bridge to the landing parking lot, crews will wrap up removing concrete and excavating electrical conduits. New conduits will be installed. Next week, crews will move on to install sidewalks and replace asphalt along curblines and road crossings.
White added that the village has been in contact with CSX about the reflective delineators at the Main Street railroad crossing. The village is ready to purchase the delineators and will coordinate with CSX for flaggers during the work.