Construction Updates Coming to Town Hall & the Perinton Community Center
Beginning the week of May 18, the Town of Perinton will launch a multi‑phase project to upgrade the entrances, sidewalks, parking areas, lighting, drainage, and landscaping around Town Hall and the Perinton Community Center. These improvements are designed to enhance accessibility, pedestrian safety, and the overall visitor experience at this busy community campus.
Tentative Construction Timeline
- Phase 1: Town Hall / Community Center North Entrance
May 18 – July 1 - Phase 2: Center (Court) Entrance
July 1 – July 31 - Phase 3: Community Center Main Entrance
August 1 – September 30
The schedule is tentative and may shift based on weather or site conditions, town officials note that the phased approach is designed to minimize disruption for residents. In addition some entrances, sidewalks, parking areas, and traffic patterns will be temporarily adjusted throughout the project.
Town Hall and the Community Center will remain open, and all recreation programs and town services will continue as scheduled. Visitors are encouraged to follow posted signage and allow a few extra minutes when arriving.